ALTA ENVIRONMENTAL
  • Home
  • Services
    • Air Quality
    • Building Sciences
    • Environmental Health & Safety
    • Site Assessment, Remediation & Closure
    • Water Resources
    • Geographic Information Systems
    • Safety & Industrial Hygiene
  • Markets & Clients
  • News & Media
    • Tools & Resources
    • Publications
    • Presentations
    • Newsletters
  • Company
    • About Alta
    • Our Team
    • Careers
    • Sustainability Policy
    • Employee Portal
    • Client Portal
  • Contact
  • Home
  • Services
    • Air Quality
    • Building Sciences
    • Environmental Health & Safety
    • Site Assessment, Remediation & Closure
    • Water Resources
    • Geographic Information Systems
    • Safety & Industrial Hygiene
  • Markets & Clients
  • News & Media
    • Tools & Resources
    • Publications
    • Presentations
    • Newsletters
  • Company
    • About Alta
    • Our Team
    • Careers
    • Sustainability Policy
    • Employee Portal
    • Client Portal
  • Contact

Navigating California’s Construction General Permit for Storm Water Discharges

1/23/2017

 
Storm Water Pollution Prevention Plan
Your quick guide to the process… SWPPP Timelines!

Identifying your need for coverage: Will your project disturb more than 1 acre of soil? If so, a state Permit is required.

​
Preparing a Storm Water Pollution Prevention Plan (SWPPP): Coordinating project information with your Qualified SWPPP Developer (QSD) early in your planning process will improve the Project’s compliance throughout the project and save schedule and money.
Filing the Notice of Intent: Submitting all the Permit Required Documents and paying the Annual Fee prior to initiating any construction activities (including demolition).

Perform routine and storm related inspections and sampling: Work with your project required Qualified SWPPP Practitioner (QSP) to ensure all documentation and Best Management Practices (BMPs) are in place, effective and appropriate.

File Annual Reports: The reporting year runs July 1 – June 30. All active Permitted projects must file an Annual Report prior to September 1.

File Notice of Termination (NOT): When the Project no longer poses a threat to storm water quality (all construction related activities and materials are completed/removed from the project site and all exposed soil areas are stabilized) the Permit can file it’s NOT.

Project Termination: The Regional Board accepts the NOT application and closes the Permit. All records must be maintained for 3 years by the permit holder.

ALTA’s team of QSDs and QSPs can manage all of these tasks so that your construction personnel can focus on what they do best: BUILD!

​Schedule a project review or project design consultation today! Click here to request your site review! Or call me at 562-495-5777.  

​Matthew Renaud: CPESC #6156, QSD/P #0740

Comments are closed.